Item planning contains information about the plan method, production nature and other production related details.
Fields & its description:
- Plan Method
Select the plan method for the item which maybe:
MRP – Based on Material Requirements Planning method.
Min/Max – Based on minimum or maximum stock.
ROL – Reorder level where inventory level at which a company would place a new order.
- MRP Method
If your plan method is MRP then specify the MRP method in this field. There are three classifications:
MPS – Master Production Schedule
DRP – Distribution Resource Planning
MRP – Material Requirements Planning
The plans maybe single or a combination, so select the option that most suits your organization.
- Make or Buy
Select if the item is manufactured or bought.
- Production Nature
- Safety Method
If your choice is quantity then it means the safety method is immediate, Days if grace days are allowed for minimum stock kept in waiting.
- Safety Level
Enter the safety level of the item.
- Planner
Select the planner name of the item in this field.
- Plan Group
The item must belong to a specific manufacturing plan group. E.g. Sheets Group, Cubicles Group, etc.
Lead Time
Lead time is the time interval it takes from initiation to execution of the manufacturing of a product.
Revisions
- May 20, 2015 @ 11:45:56 [Current Revision] by vv
- May 20, 2015 @ 11:45:56 by vv
- May 20, 2015 @ 11:41:27 [Autosave] by vv
- May 20, 2015 @ 11:32:52 by vv
- May 20, 2015 @ 11:25:43 by vv
- May 20, 2015 @ 11:00:10 by vv
- May 20, 2015 @ 10:58:28 by vv
- May 20, 2015 @ 10:23:09 by vv
- May 20, 2015 @ 09:25:58 by vv
- May 20, 2015 @ 09:21:52 by vv
- May 20, 2015 @ 09:07:53 by vv
- May 20, 2015 @ 09:06:47 by vv
- May 20, 2015 @ 07:53:29 by vv
- May 20, 2015 @ 07:37:02 by vv