Navigation Path: Planning>Transaction>Master Schedule Detail
1.Follow the above steps to open the ‘Master Schedule Detail’ screen.

2. In the ‘Master Schedule’ field enter the already created master schedule listed in the drop-down list and click ‘Load’.

3. This popup helps the user to filter using various options.
a. Forecast Filtering:
i. When the popup appears, tick/untick the ‘Forecast’ button to use the created forecast.

ii. In the ‘Forecast’ drop-down list select the created forecast and click Apply.

b. Biz Transaction Filtering (To be done only after Step 3b):
I. Tick/untick the safety stock as required. Enabling/disabling safety stock includes/excludes the buffer stock in planning.

ii. In the ‘Class’ text field firstly remove the preset classes and then choose the desired type of class from the drop-down list for planning.

iii. In the ‘BizTransaction’ field choose the relevant constituent related to the Class.

iv. In the ‘Type’ text field choose the constituent as shown in the dropdown list.

v. Click ‘Apply’ which leads to the main screen.

4. From the main Master Schedule Detail screen, choose the preset Master Schedule from the drop-down list.

5. Choosing the Master Schedule lists the items planned in the grid.

6. In the lower tabular column fill the necessary details to complete the Master Schedule Detail process.
Source Type | Indicates the source of the entry (i.e. Forecast, Sale Order, Direct Entry, Master Schedule, Safety Stock, Others) |
From | Select the starting date from which the Master Schedule is applicable. |
To | Select the ending date to which the Master Schedule is applicable. |
Days | Autogenerated when ‘From’ and ‘To’ dates are provided |
Daily Quantity | Represents quantity to be produced daily |
Total Quantity | Calculated automatically (Total Quantity=Days*Daily Quantity) |
Balance Quantity | Represent remaining quantity calculated automatically |
Plan Quantity | Indicates Planned Quantity |
Party | This field represents whichever party the Master Schedule is allocated. |
Allocation | Indicates the work order to be allocated to the Master Schedule |
Remarks | Add any descriptive comments if needed |

7. Click ‘Save’ to store the Master Schedule Detail.

Contents
Revisions
- December 12, 2022 @ 05:43:54 [Current Revision] by admin
- December 8, 2022 @ 10:03:43 by arul
- December 8, 2022 @ 10:02:54 by arul
- December 8, 2022 @ 09:31:09 by arul
Revision Differences
There are no differences between the December 8, 2022 @ 10:03:43 revision and the current revision. (Maybe only post meta information was changed.)